Key Milestones of Tarim 1.2 million Ton Ethylene Project Completed

2024-7-22

On July 19th, the radiation chamber of the first cracking furnace of the 1.2 million tons/year Phase II ethylene plant in Tarim was successfully lifted into place, achieving the step one milestone of the project construction on July 30th. This marks the beginning of the installation phase of the Tarim Phase II ethylene plant, setting a good example for the subsequent construction of the project.

The Dushanzi Petrochemical Tarim Phase II Ethylene Project is an "oil conversion" project planned and promoted by Dushanzi Petrochemical Company in response to the national call to "increase oil and gas exploration and development efforts" and "develop Xinjiang southward", implementing the high-quality development deployment of the group company¡äs upstream and downstream integration and fully tapping Tarim¡äs rich, diverse, stable and reliable light oil and gas resources. The ethylene plant, as the "leading" unit of the entire site, has a total of 7 cracking furnaces, including 2 gas furnaces and 5 liquid furnaces. Each cracking furnace consists of 2 radiation chambers.